|
After years of waiting to find a site, get a plan together,
and obtain permission from the county to move forward, the
Person County Board of Education is once again on hold where
a new bus garage is concerned.
Larry King, director of environmental services for Person
County Schools, told the school board during its regular April
meeting Thursday that the work is running about three months
behind.
The original completion date for the project was March 3.
King said the contractor, E.M. Wilkerson and Sons, asked for
an extension that will run the completion target out to May
1.
At that time, if the project is not complete, the contractor
will go into a penalty phase and be charged $200 per day for
each day the work is not completed.
King told the school board Thursday night that he was not
optimistic about the contractor meeting the May 1 deadline.
He said that as of April 1, steel framework was in place,
interior block walls were complete in the shop area and office
wall construction was in process. Also, said King, the fence
around the property was about two-thirds complete; landscaping
was about 50 percent done; and gravel for bus parking was
about 35 percent complete. Last week, said King, about 90
percent of the roof was complete.
The contractor has said he is behind schedule, according
to King, because of delays by the state Department of Insurance.
At the onset of the project, the DOI had to approve the manufactured
building drawings for the metal building that will serve as
the garage. Without that approval, the contractor could not
secure a Person County building permit. The contractor asked
for an additional 115 days, King said, but architects at LS3P
Boney, the firm overseeing the construction, determined that
only 56 days were warranted.
Christy Hutchins, construction contract administrator with
LS3P, said that, after checking the site and talking with
Wilkerson, she did not believe the DOI had held up the project
for the 115 days Wilkerson sought.
Hutchins maintained the contractor could have moved forward
with other critical path work such as preparing
for footings, working on the fencing and getting utility work
done.
Wilkerson claimed that, without the building permit, he could
not move forward, Hutchins said, But we say no. He could
have worked during the time he was awaiting word from
the DOI and for the building permit to be issued.
As it stands now, said Hutchins, May 1 should be the substantial
completion date, meaning that all work except punch
list items should be done by then. After that, she said, the
contractor would have 30 days to final completion.
Beginning May 1, said Hutchins, if the work is not complete,
there could be two separate penalties for the contractor.
After May 1, if substantial completion is not accomplished,
he will be penalized $200 a day to the point at which
we can grant substantial completion, she said. After
that time, the penalty would be $100 per day until we
can acquire completion.
Once the project is completed, it will end a six-year quest
to replace the aging bus garage on Leasburg Road. For the
past several years, the large buses in use do not fit into
the bays at the old garage.
The Person Board of County Commissioners agreed to fund the
new bus garage as part of a package of county capital improvement
work. Wilkerson submitted the low bid of $2.1 million for
the job in July 2007.
|